My contractor was supposed to start work on our house first week of June (stone patio, painting the inside of the house, some electric work and tile work). He didn't show up that week and we called him the very first day to inquire about it. Well, he says "oh sorry, i hurt my hand 4 WEEKS AGO, and so i'm running two weeks behind." He didn't bother to call us after his injury which I thought was very unprofessional.
He's been very lazy about staying in touch with us about the projects and tries to weasel his way out of some work days. I do not feel that we should pay him the full amount per our contract. He is 4 weeks behind on his project (per our contract) and we are truly annoyed. We have patio stone sitting on our driveway for almost 6 weeks...its ridiculous.
How do I tell him (at the end) that we are not paying him the full amount? Is it legal? I think it should be since he didn't fulfill his part of the contract time-wise.
2007-07-11
14:26:51
·
9 answers
·
asked by
Gumnaam1
3
in
Decorating & Remodeling