Brand new $60K garage, part II. Started having serious humidity and ice build up (reside in cold climate -10 degrees below 0 today) in my brand new heated and insulated 26 X 30 garage. Ice formed on the wall interior between the ceilings and wall. Humidity was always running high in the garage etc. Called a building inspector out and he crawled over everything and found two problems. The builder never baffled off the insulation near the eve and the ridge vent was covered and blocked by insulation. The insulation had pushed up in many spots along the roof sheathing and therefore between this and the ridge vent being blocked, no airflow circulates through. The inspector wrote up the report and my builder said he would take care of it when he could!
1. My warranty of this garage is over in 45 days, so do I demand he finish it by then, or will he still be legally bound if he does not? To me warranty implies the structure was built right, this was not?
2007-01-09
12:18:41
·
4 answers
·
asked by
Anonymous