The problem: Julio works as a quality control expert in a beverage factory. The assmebly line that he monitors produces about 20,000 bottles in a 24 hr period. Julio samples about 120 bottles and hour and rejects the line if he finds more than 1/50 of the sample to be defective. About how many defective bottles should Julio allow befor rejecting the line?

2007-09-28 05:16:10 · 3 answers · asked by krissybug19 4 in Education & Reference Homework Help

I believe I can get the answer on my own, I am having trouble in how to write the formula to get me to that point.

2007-09-28 05:28:01 · update #1

3 answers

If you copied it correctly it is simply 1/50 of the sampling. Do the calculation.

2007-09-28 05:22:24 · answer #1 · answered by epaphras_faith 4 · 1 1

If he samples 120 bottles an hour and if he finds 1/50 th of the sample defective, it comes to 2.4 bottles, but since you can't have 2.4 bottles, he has to reject if he finds more than 2 bottles (3 or more) defective.

2007-09-28 05:26:38 · answer #2 · answered by Swamy 7 · 0 0

2.4

2007-09-28 05:25:48 · answer #3 · answered by mrsgollum 2 · 1 0