Here's a quick answer that makes intuitive sense. If you took 4 cubic meters of gravel, 2 cubic meters of sand, and one cubic meter of cement you would get 7 cubic meters of the concrete you need.
But you don't want 7 cubic meters. You want ten which is 10/7 of what you get this easy way. So just multiply each measurement by 10/7 = 1.43
That gives you 5.71 cubic meters of gravel and 2.86 cubic meters of sand, and 1.43 cubic meters of cement.
2007-05-23 10:56:40
·
answer #1
·
answered by Rich Z 7
·
0⤊
1⤋
Let C be the amount of cement.
Amount sand 2C
Amount gravel 4C
Total 7C = 10. So, C = 10/7, sand is 20/7, and
gravel is 40/7 cubic meters. Check: 40/7 + 20/7 + 10/7 = 10.
2007-05-23 10:47:30
·
answer #2
·
answered by knashha 5
·
0⤊
0⤋
First, you need to divide the 10 m^3 into 7 equal parts (4+2+1).
10/7 = 1.43
Now:
o gravel = 4 x 1.43 = 5.72
o sand = 2 x 1.43 = 2.86
o concrete = 1 x 1.43 = 1.43
Add them all up and you get 10.01 m^3 (a bit of round-off error)
2007-05-23 10:43:27
·
answer #3
·
answered by one_n1ce_guy 4
·
1⤊
0⤋
4/7 x 10 = gravel
2/7 x 10 = sand
1/7 x 10 = cement
2007-05-23 10:46:40
·
answer #4
·
answered by Anonymous
·
1⤊
0⤋
Total ingredients = 7m³.
4/7ths of 10 = 40/7 = 5.7m³ of Gravel.
2/7ths of 10 = 20/7 = 2.9 m³ of sand
1/7th of 10 = 1.4 m³ of cement.
Total = Exactly 10 m³
2007-05-23 10:54:59
·
answer #5
·
answered by Norrie 7
·
0⤊
0⤋
The correct answer is you call the ready mix plant and get your 10 cubic meters (or yards here in the states) and they figure out the correct proportions to supply the mix you asked for.
2007-05-23 10:49:41
·
answer #6
·
answered by Jeffrey S 6
·
0⤊
0⤋
no one is right...this ratio is by WEIGHT, not volume. so we need to find out the specific gravity of each then do the math.
2007-05-23 11:37:14
·
answer #7
·
answered by Anonymous
·
0⤊
1⤋
ummm ... 10m3 of each. The ration didn't change, just the multiplyer did. If you have a constant m and you need 10m, then you would need 10 x each item.
2007-05-23 10:41:22
·
answer #8
·
answered by Anonymous
·
0⤊
3⤋