8.The relationship between the budgeted actual cost, actual work completed and work planned will determine the
Answer:
a. Cost estimate at completion
b. Cost performance index
c. Schedule performance index
d. Schedule estimate at completion
9.The measurement which best shows the difference between actual work and actual costs is
Answer:
a. Cost variance
b. Schedule variance
c. Percent over or under
d. CPI
10.Your most recent project status report contains the following information:
EV = 3,000
AC = 3,500
PV = 4,000
The schedule variance is:
Answer:
a. - 500
b. - 1,000
c. + 500
d. + 1,000
11.One common way to compute estimated at completion (EAC) is to take the project budgeted at completion and:
Answer:
a. divide it by the schedule perofrmance index
b. divide it by the cost performance index
c. multiply it by the schedule performance index
d. multiply it by the cost performance
2007-02-24
16:56:36
·
1 answers
·
asked by
Anonymous
in
Science & Mathematics
➔ Mathematics