how long will it take them if they work together?

This is harder than it looks, and i feel like an idiot for not knowing how to approach it.

2007-01-31 12:59:54 · 5 answers · asked by ? 1 in Science & Mathematics Engineering

5 answers

Bob's rate = 1 wall / 8 hours
Butch's rate = 1 wall / 5 hours

(Bob + Butch)'s rate = 1/8 + 1/5 wall/hours = (5+8)/(5*8) wall/hour = 13/40 wall/hour

number of walls built = time * (rate of building walls)
we want 1 wall and we calculated the rate, so solve for time:

time = 1 wall / (13/40 wall/hr) = 40/13 hour = 3.08 hour

gatorbait's answer below can't be right (6.5 hr). why not just let Bob sleep and have Butch do it in 5 hour!! if it takes longer, than Bob isn't building walls, but tearing them down. always do a "sanity check" on your answer.

2007-01-31 14:34:39 · answer #1 · answered by Anonymous · 0 0

Bob and butch build 2 walls in 8 + 5 hours = 2 walls in 13 hours.

So...working together they can build 1 wall in 13/2 = 6 1/2 hours

2007-01-31 14:35:28 · answer #2 · answered by gatorbait 7 · 1 1

Bob's rate is 1/8 and Butch's is 1/5. So I think you can add the rates to get the total as:
(1/8) + (1/5) = 1/X (that is one wall in X hours)

solve for X to get the number of hours:
(13/40) = 1/X

X = 40/13 hours. you might want to check my work.

2007-01-31 14:20:26 · answer #3 · answered by joe_ska 3 · 1 0

3 hours

2007-01-31 14:15:16 · answer #4 · answered by leela manohar 1 · 0 0

I think, if they were work together, they will need around 3.5 to 4 hours to finish what they started. But, it all matter of cooperation and tolerence between them.

2007-01-31 14:35:49 · answer #5 · answered by Black Eye Peace 2 · 0 1