English Deutsch Français Italiano Español Português 繁體中文 Bahasa Indonesia Tiếng Việt ภาษาไทย
All categories

I'm new at drywall installation. I was wondering which to sheetrock first. The ceiling or the walls. Does the ceiling then rest on the walls(sheetrock)?

Thanks.

2006-11-04 11:33:23 · 8 answers · asked by samw3 2 in Home & Garden Decorating & Remodeling

8 answers

always do the lids first. (ceiling)the wall board holds up the corner. And you get the harder part out of the way.

2006-11-04 16:36:37 · answer #1 · answered by carolinatinpan 5 · 0 0

It's common practice to do the ceilings first. It's nice to have the sheetrock on the walls to hold up the ceiling but not absolutely necessary.

Just be sure to put in enough screws and when screwing, try not to drive the screws too far so the paper tears. If the screws tear the paper, they're more inclined to show up in a few years.

2006-11-04 11:41:33 · answer #2 · answered by Matrix 3 · 0 0

No, it creates a joint. I would advise doing your walls first, then the ceiling. You can use a screw gun to attatch your sheetrock to the ceiling cross beams. But generally the ceiling does not 'sit' on the wall. After you lay your sheetrock to on wall and ceiling, use joint compound to fill in the seams in the corners and ceiling, and to cover the screws. apply a thin coat and use a damp sponge to remove excess to create a smooth serface. After the compound dries (allow to dry overnight if possible) if necessary use a fine grade sandpaper to smooth any roughness from the compound and paint surfaces. Another option is to use caulk for corners and to fill screw holes. Follow same procedure as above.

2006-11-04 12:02:55 · answer #3 · answered by Marsha Blue 2 · 0 1

ceiling first so as to have a tight seam at the wall, it does not really "hold it up" per say but allows the installer not to have to cut the rock tight to the wall when installing the ceiling rock.....always cut ur ceiling rock 1/4" less then ur measurement to allow easier installation....if u will check my answers page i detail this in a earlier question......


lic. gen. contractor

2006-11-04 11:57:48 · answer #4 · answered by bigg_dogg44 6 · 0 0

Yes... do the ceilings first then the walls.. it is to make the joints seal better when you fill them in with the mud

2006-11-04 11:34:59 · answer #5 · answered by Anonymous · 1 0

there is basically one answer to the undertaking. in case you do it good the 1st time in maximum circumstances you will no longer ought again to it. you % a intense scraping knife to dig out the cracks. this suggests digging them out from the commencing off to the top of each crack no remember how small. you need to dig them out heavily deep, do no longer undertaking approximately making a trench there. The deeper you circulate the less probably it is going to return. Than: First technique fill it in with airborne dirt and dirt (puddy) easily with a puddy knife. you will ought to do this approximately thrice until ultimately this is crammed and forestalls from receding. to be sure it does no longer return: Take drywall tape and upload one extra layer of puddy over that making specific each little thing is mushy. After a effective sanding and portray you need to no longer be waiting to work out the place the crack replaced into. sturdy success!

2016-11-27 19:24:32 · answer #6 · answered by Anonymous · 0 0

hehe I've seen it done BOTH ways but more times they do the walls first...(just my experience)

2006-11-04 13:28:12 · answer #7 · answered by Anonymous · 0 0

yes

2006-11-04 11:34:40 · answer #8 · answered by Mary Smith 6 · 0 0