You can check out the NY DOT website for traffic conditions for any area. This is what they are currently showing for Delaware County:
Route 28 in the Town of Meredith and Route 357 in the Town of Franklin
PROJECT: Bridge Replacements
START DATE: August 2005
SCHEDULED COMPLETION: October 2006
WORK ZONE: The work limits for this project are located on Route 28 over Houghtaling Creek between Coe Road and Smith Hill Road, and on Route 357 over Treadwell Creek between County Road 14 and Chamberlain Hill Road.
TRAFFIC CONTROLS: Temporary lane closures, a two lane on-site detour at Route 28, and alternating single lane traffic controlled by a signal on Route 357.
NYSDOT D259862
CONTRACTOR: Ketco, Inc.
CONSTRUCTION COST: $3,158,519
Route 28 Curve Flattening
PROJECT: The project consists of the realignment of a substandard segment of Route 28.
START DATE: April 2006
SCHEDULED COMPLETION: November 2006
WORK ZONE: 400 meters on NYS Route 28 at the intersection with County Route 6, in the Town of Middletown.
TRAFFIC CONTROLS: Temporary signals may cause minor delays.
NYSDOT D260067
CONTRACTOR: New Century Construction, LLC
CONSTRUCTION COST: $788,888
Route 28 Pavement Resurfacing
PROJECT: The project consists of the resurfacing of 4.2 mi of Route 28 in the Town of Middletown, with minor drainage improvements.
START DATE: May 2006
SCHEDULED COMPLETION: November 2006
WORK ZONE: Route 28, from Cloverville to Arkville, in the Town of Middletown.
TRAFFIC CONTROLS: Flaggers and daily lane closures may cause minor delays.
NYSDOT D260174
CONTRACTOR: Cobleskill Stone Products, Inc.
CONSTRUCTION COST: $2,076,472
General Bridge Repairs 2005, Delaware, Schoharie and Sullivan Counties
PROJECT: The project consists of bridge repairs on Route 30 in Middleburgh, Route 55 in Neversink and Route 206 in Walton.
START DATE: March 2006
SCHEDULED COMPLETION: November 2006
WORK ZONE: At each bridge and approaches.
TRAFFIC CONTROLS: A temporary signal will be used in Walton. At Middleburgh and Neversink, flaggers and daily lane closures may cause minor delays.
NYSDOT D260054
CONTRACTOR: Fahs Construction Group
CONSTRUCTION COST: $3,398,826
Interstate 88 Pavement Rehabilitation, Delaware and Otsego Counties
PROJECT: The project consists of 9 km of asphalt concrete pavement rehabilitation on Interstate 88 and Route 991H in the Town of Sidney and Village of Unadilla.
START DATE: May 2006
SCHEDULED COMPLETION: June 2007
WORK ZONE: On Interstate 88, beginning 1 km west of Exit 10 and continuing easterly to 2 km east of Exit 11. On Route 991H, from the Exit 10 ramps to Route 7, in the Village of Unadilla.
TRAFFIC CONTROLS: Daily lane closures until traffic is crossed over the median with a single lane in each direction. A reduced speed limit is in effect.
NYSDOT D260153
CONTRACTOR: Green Island Contracting, LLC
CONSTRUCTION COST: $9,461,140