___________Machine A_____Machine B
Time (h)______12___________8
Rate of work__X/12_________X/8
(units / h)
After 2 h, work done by A = X/6 units
Remaining work = 5X/6 units
Working together, the rate of work is:-
X/12 + X/8 = 5X/24 units
Time = (5X/6) / (5X/24) h
Time = (5X/6) x (24 / 5X) h
Time = 4 h
Will take 4 hours after they start working together.
But B worked for 2 hours beforehand.
Total = 6 h
2007-12-30 05:35:42
·
answer #1
·
answered by Como 7
·
1⤊
1⤋
Here's another way of looking at it:
Since it takes Machine A 12 hours to complete a full job, Machine A completes 1/12 of the job every hour.
Since it takes Machine A 8 hours to complete a full job, Machine B completes 1/8 of the job every hour.
In the first two hours: A does 0, B does 2/12
Hour3: A does 1/8, B does 1/12
Hour4: A does 1/8, B does 1/12
Hour5: A does 1/8, B does 1/12
Hour6: A does 1/8, B does 1/12
Totaling A's amount of the job gives you (1/8 + 1/8 + 1/8 + 1/8) = 4/8 = 1/2
Totaling B's amount of the job gives you (2/12 + 1/12 + 1/12 + 1/12 + 1/12) = 6/12 = 1/2
A's 1/2 of the job + B's 1/2 of the job gives you the whole job. Therefore, the total time it takes both machines to finish the job is 6 hours.
2007-12-29 21:40:52
·
answer #2
·
answered by McMurphyRP 3
·
0⤊
0⤋
Machine A completes 1/12 of the job every hour
Machine B completes 1/8 of the job every hour
Working together, machines A and B complete 1/12 + 1/8 = 5/24 of the job every hour
Machine A works for 2 hours and completes 1/6 of the job
5/6 of the job is left
(5/6)/(5/24) = 24/6 = 4
Machines A and B would require 4 more hours to complete the rest of the job.
Taking into account the original 2 hours, the total time required to complete the job is 6 hours.
2007-12-29 21:35:17
·
answer #3
·
answered by gudspeling 7
·
0⤊
1⤋
working alone, A will have done 1/12x2 = 1/6 part of the job. the work done here is equal to the rate (for A, this is 1 job in 12 hours, or 1/12) times the time, which is 2 hours. hence, A does 1/6 of the job alone in the first part.
when B comes in, both A and B work together, so that the work they do together ought to be 5/6 of the total job. If we let x be the time they work together to complete the rest of the job, then the work of A = (1/12 times x), and the work of B is (1/8 times x), and so we have:
1/12x + 1/8x = 5/6
simplifying by multiplying both sides of the equation by the LCD = 24, we get
3x + 2x = 20, and x =4 hours. The total time to do the job (from the start when A started alone) is thus 2+4 = 6 hours.
2007-12-29 21:51:05
·
answer #4
·
answered by Mama Ann 2
·
0⤊
1⤋
A does 1/12 of the job an hour
B does 1/8 of the job an hour
After 2 hours, A will have completed 2 * 1/12 = 1/6 of the job. That leaves 5/6 to be done.
Let T be the number of hours remaining:
(1/12 + 1/8)T = 5/6
Multiply everything by 24 to get rid of denominators:
(2 + 3)T = 20
5T = 20
T = 4
So A will work alone for 2 hours, then A and B will work together for 4 more hours ---> total of 6 hours.
2007-12-29 21:33:44
·
answer #5
·
answered by Puzzling 7
·
1⤊
1⤋
Let t = time to complete the job after machine B had worked in 2 hours.
2(1/8) + t(1/12 + 1/8) = 1
1/4 + t(2/24 + 3/24) = 1
1/4 + 5/24t = 1
5/24t = 3/4
t = 18/5 or 3.6
Answer: 3.6 hrs or 3 hrs & 36 min after machine B had worked 2 hours.
The total time used to complete the job was: 3 hrs & 36 min for machine A and 5 hrs & 36 min for machine B.
Proof:
2(1/8) + 3.6(1/12) + 3.6(1/8) = 1
0.25 + 0.3 + 0.45 = 1
1 = 1
Machine A hrs + machine B hours = 1 job
3.6(1/12) + 5.6(1/8) = 1
0.3 + 0.7 = 1
1 = 1
2007-12-29 21:49:25
·
answer #6
·
answered by Jun Agruda 7
·
3⤊
0⤋
A completes 1 job per 12h. After 2 hours, A has completed
    2h · (1job/12h) = (1/6)job
leaving (5/6) of the job to be completed.
Working together, A and B can complete
    1job/12h + 1job/8h = 5jobs/24h
A and B can complete the remaining (5/6) job in
     (5/6) job * (24h/5jobs) = 4h
Total time for job = 6h
2007-12-29 21:42:42
·
answer #7
·
answered by DWRead 7
·
0⤊
0⤋
6 Hours please pick me i need to get to level two
2007-12-29 22:12:38
·
answer #8
·
answered by katieee. 2
·
0⤊
4⤋