Let X = area to be washed.
____________Monica_____Bill
Work rate_____X________X/2
Working together work they clean (3/2)X in 1 hour
(3/2) X<---> 1 hour
X<--------->X / (3/2)(X) hour = 2/3 hour
It will take them 40 min
2007-10-19 19:55:52
·
answer #1
·
answered by Como 7
·
0⤊
0⤋
monica can do 1 car per hour
bill can do 1/2 a car per hour
so together they can do 1 and a half cars per hour
or 3/2 cars/hour
so (1 car)/ (3/2 cars/hour)= 2/3 hour.
Together they can wash a car in 2/3 hour.
or 2/3 hours * 60 min/hour= 40 minutes
2007-10-20 01:13:39
·
answer #2
·
answered by zenock 4
·
0⤊
0⤋
Let x be the part of the job done
x/1 + x/2 = 1
(3/2)x = 1
x = 2/3
it will take them 40 minutes to wash one car
2007-10-20 01:12:18
·
answer #3
·
answered by rEi 3
·
0⤊
0⤋
Bill's rate is 1/(2 hr/car) or .5 car/hour
Monica's rate = 1 car/hour
Monica + Bill rate together = 1 car/hour + .5 car/hour
= 1.5 car/hour
Rate (Time) = # of cars washed
1.5 car/hr (time) = 1 car Divide both sides by 1.5
time = 1 car / (1.5car/hr)
time = .666666667 hours
Convert to Minutes
= .666666667 hours (60 minutes/hour)
= 40 minutes ANSWER
2007-10-20 01:11:00
·
answer #4
·
answered by r r 5
·
1⤊
0⤋
1/1 + 1/2 = 1/x where x = time for both doing this together
3/2 = 1/x
3x = 2
x = 2/3 hr
2007-10-20 01:12:56
·
answer #5
·
answered by duffy 4
·
0⤊
0⤋
40 minutes
2007-10-20 01:11:17
·
answer #6
·
answered by Anonymous
·
0⤊
0⤋
tell them to both wash 1 car and time them.
2007-10-20 02:51:27
·
answer #7
·
answered by seaniquanzo 2
·
0⤊
0⤋
40 minutes.
2007-10-20 01:12:14
·
answer #8
·
answered by crazyramsfan 1
·
0⤊
0⤋
2 hours...Why would Monica wash the car when she can get Bill to do it???? Silly Rabbit!!!!
2007-10-20 01:08:48
·
answer #9
·
answered by imshorty 2
·
1⤊
1⤋
If they are washing at the same time, two hours.
2007-10-20 01:07:53
·
answer #10
·
answered by Nicole L 3
·
0⤊
1⤋