A general contractor is hired by a principal to erect an large art exhibit.
The gen'l contr. hires subcontractors to build the exhibit and acquire rented and loaned items.
The gen'l contractor is paid an override from the principal on what is charged by the subcontr. to do the work.
The principal paid the gen'l cont. and then the gen'l paid the subcont..
The principal then decides to extend the display period beyond what was originally contracted for with the gen'l, but does so w/out going through the gen'l.
The principal goes DIRECTLY to the subcont. doing an "end run" around the gen'l. contr.
If the gen'l would have known the display period would have included this additional time, the original cost to the principal would have been greater thus allowing the gen'l a larger fee.
Does the gen'l have a cause of action against the principal for the lost fee?
Is there case law to support the gen'l's claim?
2007-09-19
12:51:51
·
4 answers
·
asked by
atlasmv
1
in
Politics & Government
➔ Law & Ethics