Calendar days include weekends and holidays. Working days include only those days normally worked in that industry (Monday through Friday for most people in the US)
2007-09-01 17:01:32
·
answer #1
·
answered by MICHAEL R 7
·
0⤊
1⤋
A calendar day refers to all days on a calendar, including weekends, which are not considered work days.
There are two reasons (that I can think of) that someone would specify calendar days --
1. To contrast it with work days.
If today is September 1, and it will arrive by September 10, you can say it will take 10 calendar days.
2. To differentiate from a 24-hour period.
If something is going to take two days, it may take less than 48 hours, but it will be the second day on the calendar.
2007-09-02 00:09:32
·
answer #2
·
answered by Coach McGuirk 6
·
1⤊
0⤋
No. It refers to all days. Monday to Monday is 5 work days but 7 calendar days.
2007-09-01 23:49:40
·
answer #3
·
answered by elysian fields 3
·
1⤊
1⤋
No they do not.
15 calendar days is a little more than 2 weeks.
15 working days is 3 weeks.
2007-09-01 23:49:54
·
answer #4
·
answered by Anonymous
·
3⤊
0⤋
Working days are Monday thru Friday - Calendar days are all days, i.e Thursday to Thursday is 5 working days but 7 calendar days.
2007-09-01 23:49:44
·
answer #5
·
answered by Anonymous
·
1⤊
1⤋
Time periods of five days or less refer to working days; time periods of more than five days refer to calendar days
2007-09-01 23:48:53
·
answer #6
·
answered by innamorta2000 3
·
0⤊
2⤋