I need a formula and a website to solve this problem. This is what the paper says:
Tunnels have been used hroughout history for various purposes, such as irrigation and transportation.
Boring Brothers, Inc. has a contract to dig a tunnel through a mountain to accommodate the construction of a major highway. Crew A starts at the west end and digs at a rate of 9 meters per day. Crew B starts at the east end two days after Crew A and digs at a rate of 12 meters per day.
Then it has a piocture of the tunnel being plowed. Crew A is on the left side and is slightly shorter than Crew B's tunnel residing on the right side. The whole mountain length is 2118 meters.
Are these rates reasonable? I need a formula and a website please!!