50 men complete work in 20 days
so, 50x20 = 1000 men-days

If 10 mens left after 5 days work,
so, 50x5=250 men-days already done

1000 = 250 + 40 men x n days
40n = 750
n = 18.75 days
18.75 days more to complete work

Total days to complete work
= 5 + 18.75 = 23.75 days

2007-02-01 20:56:21 · answer #1 · answered by seah 7 · 4 0

Let x = remaining number of days to complete work.

Total work = (50 men)(20 days) = 1000 man days

50*5 + (50 - 10)x = 1000
250 + 40x = 1000
40x = 750
x = 750/40 = 75/4 = 18.75 additional days

2007-02-01 21:25:28 · answer #2 · answered by Northstar 7 · 0 0

We know that,
50 men complete the work in 20 days.
Quantum of work completed in 5 days = 25%
Work balance = 75%
40 men will complete the balance work in = 50 x 20 x 0.75/40
= 18.75 days
ANSWER : Thus, 40 men will take (18.75 - 15) = 3.75 more days

2007-02-01 23:06:06 · answer #3 · answered by Anonymous · 0 0

let the whole work be 1!
then , the ability of one worker a day is 1/20/50=1/1000

for 5 days , 50 workers worked and the work done is 1/1000*50*5=1/4 of the whole work
so the work left is 3/4!
and to finish the work with 40 men , it takes (3/4)/(40*1/1000)=
=(3/4)/(1/25)=75/4 days
75/4=18.75
so 19 days will take to complete the work

2007-02-01 21:12:30 · answer #4 · answered by happyrabbit 2 · 0 0

a million. Sugar Ray Robinson 2. Henry Armstrong 3. Roberto Duran 4. Willie Pep 5. Archie Moore 6 Harry Greb 7 Sugar Ray Leonard 8 Marvin Hagler 9 Julio Cesar Chavez 10 Wilfredo Gomez

2016-10-16 10:56:17 · answer #5 · answered by jackson 4 · 0 0

Total mandays of work = 50 x 20 = 1000 days

First five days finished work = 50 x 5 = 250 days

pending mandays of work = 750
Men in hand = 40

So required number of days = 750 / 40= 18.7 days

2007-02-01 21:04:28 · answer #6 · answered by Chungath 2 · 0 0

It's only going to take the remaining 40 men the remaining 15 days to complete the job.

2007-02-01 21:07:27 · answer #7 · answered by JSalakar 5 · 0 1

75/4 days........
After 5 days.......50 men would had completed in 15 days
i.e. 1 man would had completed in 15*50=750 days.....
But 10 men left,so rest 40 men can complete rest work in (750/40)=75/4 days.......;-)

2007-02-01 20:58:11 · answer #8 · answered by i m gr8 3 · 0 0

answer: 8 more days

1 man can finish 20/50
or 2/5

after 5 days 10 men finish 10*2/5 =4

50-10=40 men

40 men can finish 16+x days
5/5-2/5=3/5

(16+x )*5=3*40
x=8 more days

2007-02-01 21:00:01 · answer #9 · answered by iyiogrenci 6 · 0 1

25 days

2007-02-01 21:53:28 · answer #10 · answered by Anonymous · 0 0