How much would a sidewalk cost that is 3' wide, 50' long and 3" thick if the concrete is $134.50 per cubic yard and labor costs are $2.44 per square foot?


Thank you again.

2007-01-24 01:59:04 · 2 answers · asked by Still Standing 4 in Business & Finance Renting & Real Estate

2 answers

Harsh, Ogrendle.

Ok, let's think about it.

3' wide X 50' long = 150 square feet
Therefore, labor = 2.44*150 = $366

150 square feet * .25' = 37.5 qubic feet = 1.39 qubic yards
1.39*$134.5 = ~$187

Total = ~$553

2007-01-24 02:09:17 · answer #1 · answered by Anonymous · 0 0

Do your own homework. You won't learn if we do it for you.

2007-01-24 10:04:38 · answer #2 · answered by Anonymous · 0 0