Think of it this way:
In one hour,
Martha will be 1/4 = 25% done;
Jack will be 1/3 = 33% done; and
Max will be 1/5 = 20% done.
Thus, if they all work together, in one hour they will be 1/4 + 1/3 + 1/5 = 47/60 = 78% done. Thus, to finish the job it will take 60/47 hours, which is about 1 hour, 16 minutes, and 36 seconds.
2007-01-12 14:07:16
·
answer #1
·
answered by rozinante 3
·
5⤊
0⤋
I think the best way to solve a problem like this is to reason as follows:
In one hour, Martha can paint 1/4 of a house, Jack can paint 1/3 of a house, and Max can paint 1/5 of a house. So, working together, in one hour they can paint 1/4 + 1/3 + 1/5 of a house, or 47/60 of a house, and it will take 60/47 hours to paint the whole house.
2007-01-12 22:07:47
·
answer #2
·
answered by Anonymous
·
2⤊
0⤋
the trick is always in how to set the problem up
Martha paints 1/4 house/hour
Jack paints 1/3 house/hr
Max paints 1/5 house/hr
therefore
(1/4 + 1/3 +1/5) = I house painted hour
47/60 of a house painted per hour
divide 47 into 60 = 1.28 hours
1 hr 17 minutes
2007-01-12 22:11:25
·
answer #3
·
answered by tom4bucs 7
·
0⤊
0⤋
Lets see how much of a house they can paint together in one hour.
Martha can paint a house in 4 hours, so she paints 1/4 of a house in an hour
Jack can paint a house in 3 hours, so he paints 1/3 of a house in an hour
Max can paint a house in 5 hours, so he paints 1/5 of a house in an hour.
1/4+1/3+1/5=15/60+20/60+12/60=47/60, so they paint 47/60ths of a house together.
At this pace, it will take 13/47ths of an hour to paint the remainder, so the total time is 1 and 13/47ths hour, or 60/47 hour.
(That's roughly 1 hour and 16.6 minutes, if it helps)
2007-01-12 22:08:35
·
answer #4
·
answered by dennismeng90 6
·
2⤊
0⤋
Martha does 1/4 the job per hour, Jack 1/3 and Max 1/5. If they are all working together, they do:
1/4 + 1/3 + 1/5 of the job per hour. Common denom is 60
15/60 + 20/60 + 12/60 = 47/60 of the job per hour.
To complete the job, find time t such that
(47/60)*t = 1
t = 60/47 hours
2007-01-12 22:06:37
·
answer #5
·
answered by bozo 4
·
4⤊
0⤋
You add the rates.
martha's rate is 1/4 of a house/hr
jacks is 1/3 &
max is 1/5
working together the rate is
1/4+1/3+1/5=(15+20+12)/60=47/60 house/hr
painting 1 house will take 60/47 hrs=1 hr 16 min 36 sec
2007-01-12 22:40:11
·
answer #6
·
answered by yupchagee 7
·
0⤊
0⤋
It takes 4 hours for Martha to paint the house, so:
4M=H; that is, 4 hours of martha working equals a painted house.
3J=H; 3 hours of jack working equals a painted house
5A=H; 5 hours of Max working equals a painted house.
Adding M+J+A, as we are combining all their working efforts:
H/4 +H/3 +H/5=xH
x is the number of hours it takes for them all combined, H is a completed house. In other words, all three's efforts times their total working hours equals a painted house.
Therefore x= 1/4+1/3+1/5, and works out as 47/60 hours. This is 47 minutes, as an hour can be separated into 60 minutes.
Hope this helps.
2007-01-12 22:17:02
·
answer #7
·
answered by samuelll 2
·
0⤊
3⤋
martha can paint 1/4 of the house in 1hr
jack can paint 1/3 of the house in 1hr
max can paint 1/5 of the house in 1hr
in 1hr (1/4 + 1/3 + 1/5)=.783 of the house is painted
in order to get the time necessary to paint the entire house you must multiply by the reciprocal
1= .783x
1( 1/.783) = x
x=1.278 hr= 1hr 16min
2007-01-12 22:26:11
·
answer #8
·
answered by ۞ JønaŦhan ۞ 7
·
0⤊
0⤋
rate*time = work (rt= w)
m = martha's rate
j = jack's rate
x = max's rate
m = 1/4
j = 1/3
x = 1/5
(1/4+1/5+1/3) * n = w
(15/60 + 12/60 + 20/60) * n = w
47/60 *n = w
60/47 hours = 1.277 hours
2007-01-13 00:00:39
·
answer #9
·
answered by Brian F 4
·
0⤊
0⤋
4+3+5 = 12
12/3=4 hours average for each to complete the job alone.
4 hours/3 persons= 1.333 (.333*60=20 minutes) or 1 hour and 20 minutes.
I like to use decimals in my calculations, the 1 hr and 16.6 minute answers are from those using fractions, so it is a rounding difference. 19.999999 minutes to 20.
2007-01-12 22:11:42
·
answer #10
·
answered by B Jones 4
·
0⤊
1⤋