Done the prep work, compaction etc? How did you do it and how did the project come out and hold up? What did you learn that might be a good tip to help me do my own? This is in a non frost/heave climate. Thanx!

2006-12-22 05:59:51 · 2 answers · asked by Anonymous in Home & Garden Maintenance & Repairs

2 answers

NOT ON DIRT...

YOU NEED 8" OF COMPACTED CRUSHED LIMESTONE/CONCRETE BASE! THEN 2" OVERLAY!

2006-12-22 06:03:50 · answer #1 · answered by Bonno 6 · 0 0

around new england we use 8" of 3/4" crushed rock and stone dust, called 'new process', then 4" of black top 'asphalt'.

2006-12-22 15:03:42 · answer #2 · answered by car dude 5 · 0 0