4 sharp sand, 1 Portland cement - mix dry then mix in just sufficient water so a handful will just stay together when squeezed.
2006-11-12 04:24:36
·
answer #1
·
answered by PAUL H 3
·
0⤊
0⤋
yep i agree with paul h,thats what i do im a plasterer iv done floor screeds,4sharp sand,1 cement if ur gonna do it urself u should think about geting some knee pads or something for when u float it or rub it up coz it burnes ur skin abit nothing to worry about just a pain in the ****!good luck.....
2006-11-12 20:04:23
·
answer #2
·
answered by smokey 2
·
0⤊
0⤋
Dry mix the sand and cement first then make a hole in the centre of the pile and add water then mix together until it is a workable consistency
2006-11-12 11:20:33
·
answer #3
·
answered by brainstorm 7
·
0⤊
0⤋
use a paddle mixer with a 1/2 inch drill. also mix per directions on product it will seem too dry but as yoy shape it the water will come to the surface. it's just that easy
2006-11-12 10:24:36
·
answer #4
·
answered by mikeyctr6 1
·
0⤊
0⤋
visit his web sight
http://verizonsupersite.com/kwikmix1com/howto/
2006-11-12 10:05:10
·
answer #5
·
answered by aussie 6
·
0⤊