English Deutsch Français Italiano Español Português 繁體中文 Bahasa Indonesia Tiếng Việt ภาษาไทย
All categories

9 answers

An 80 lb (36.3 kg) bag yields approximately
0.60 cu ft (17 L).
Divide .60 cu ft into the 27 cu ft for the hole. 45 bags. Lots of hand mixing, go with the concrete truck.
Check out the spec/data sheets.
Hope it helps.

2006-07-16 14:09:05 · answer #1 · answered by etcher1 5 · 0 0

according to your measurements it will take exactly .78 cubic yds
in converting to cubic feet 1 cubic yard = 27 cubic feet .you need approximately 80% of that which is about 22 cubic ft .check the 80lb bags label for its yield usually a 1/2 cubic foot if thats the case you'll need about 44 bags (alot of hand mixing). Check with your local ready mix company it might be better to just have 1yd delivered ready to go . I'm partial to this idea since i drive a ready mix truck for a living.

2006-07-15 10:45:04 · answer #2 · answered by con-man 1 · 0 0

it depends on what you're trying to do with the 3x3x3 concrete. Maybe 12 bags and some gravel mix.

2006-07-15 10:32:35 · answer #3 · answered by shclapitz 3 · 0 0

3 by 3 by 3 is one yard, see how many bags per yard and youve got it

2006-07-15 10:30:15 · answer #4 · answered by Anonymous · 0 0

The weight of the bag doesn't matter, it's the volume of the mix.

2006-07-15 10:31:21 · answer #5 · answered by Anonymous · 0 0

ask Jimmy Hoffa

2006-07-15 10:30:53 · answer #6 · answered by Anonymous · 0 0

FOUR BAGS. THIS SHOULD GIVE YOU A LITTLE EXTRA, ITS BETTER TO HAVE MORE THAN LESS.

2006-07-15 10:39:50 · answer #7 · answered by him n her♥ 4 · 0 0

as many as you think

2006-07-15 10:29:51 · answer #8 · answered by Anonymous · 0 0

dunno

2006-07-15 10:29:01 · answer #9 · answered by Anonymous · 0 0