5 answers

You need 6 yards.

2006-07-12 05:03:53 · answer #1 · answered by Jack430 6 · 0 1

You would require 6cubic yards.
4inches is 0.3333 of a foot.
18x27x0.3333=161.9838cubic feet.
There are 27 cubic feet in a cubic yard so divide this by 27 and you get 5.9994 cubic yards.
Be careful though as this would only be 6 cubic yards if the concrete was laid 4 inches thick exactly and there may be some loss if the surface where the driveway is being laid is not even.

2006-07-12 05:12:29 · answer #2 · answered by Mikem 3 · 0 0

I get 6 cubic yards.

6 yards wide x 9 yards long x (1/9) yards deep

Comes out to 6.

2006-07-12 05:05:25 · answer #3 · answered by Ian M 5 · 0 0

I come up with 8 yrds

Oh well no one said I was perfect, I checked it out on the calculator and it came out to 6

2006-07-12 05:06:22 · answer #4 · answered by Jerry S 4 · 0 0

closer to 6

2006-07-12 05:04:28 · answer #5 · answered by dwh12345 5 · 0 0