Mica Co argeed to commercial storage building by september 1 for Pack Rat Storage. It was hard to predict Pack Rat's losses if the building was not completed on time. The parties estimated that Pack Rat would lose $200 in storage fee per day if the building was not completed on time. Thus, the contract required Mica to pay liquidated damages of $200 per day if work was completed late. Mica finished ten days late. Pack Rat actually lost $1800 due to the work was completed late. Mica finished ten days late. Pack Rat actually lost $1800 due to the breach. 1.Is the liquidated damage amount stated in the contract between Mica. Co. and Pack Rat Storage valid, or is it an invalid penalty? 2. How much in damages can Pack Rat recover from Mica Co.?
2006-06-27
13:52:36
·
3 answers
·
asked by
Nice girl
3
in
Politics & Government
➔ Law & Ethics