Had counters installed. We agreed to a set price with the contractor. We signed bid showing this price. We paid for the counters upon completion and now contractor wants $560.00 more for extra hours worked. At no point durring installation process did he bring up these extra hours or explain he would need even more money. Is this common practice? Do we have to pay? If we agreed to have him do this job for a set price is it our fault it took him longer and are we obligated to pay this additional amount? If this is the case every contractor could do this and always bank on additional money. No contract was signed only the original bid for work. thanks for any help.
2006-06-11
09:22:55
·
4 answers
·
asked by
wendy s
1
in
Politics & Government
➔ Law & Ethics