Figure out how many total hours of photocopying are being done, then figure out how many hours each of 8 copiers would have to work to do the same total number of hours.
[ADDED] These people saying 16 are astoundingly dumb. If it takes just 6 hours for 3 copiers, how can it take 16 hours for 8 copiers? It's NOT a proportion problem. Dummmm dum DUM dummmm.
There ARE a couple of people on this page with the right answer, though.
2006-06-05 16:23:17
·
answer #1
·
answered by BishopKlaw 1
·
0⤊
0⤋
just getting a simple guess.
6 copiers could do the job in 3 hours
9 copiers could do the job in 2 hours
so, we know the answer has to be somewhere between 2 and 3 hours.
1 job = 18 photocopy * manhours. If I have 8 men, then I divide 18 by 8.
18/8 hours = 2 2/8 = 2 1/4 hours.
2006-06-05 16:25:48
·
answer #2
·
answered by something 3
·
0⤊
0⤋
3 copiers = 6 hours
1 copier = 6*3 = 18 hours --- as 1 copier would take longer
8 copiers = 18/8 = 2.25 hours
--- as 8 copiers would take a shorter time
Note that the time taken is inversely proportional to the number of copiers.
2006-06-05 16:26:03
·
answer #3
·
answered by Kemmy 6
·
0⤊
0⤋
4
2006-06-05 16:23:30
·
answer #4
·
answered by NS42day 4
·
0⤊
0⤋
first, an assumption must be made (or, it has to be implied) that each typist would uniformly accomplish the job, working alone, in x hours... let the hourly rate for each typist be 1/x; then, working together, the job will be accomplished by 3 typists at the hourly rate of 1/5; that is,
3(1/x) = 1/5
which yields x = 15
i.e. each typist, working alone can complete the job in 15 hours... so, now, for 8 typists, working together, let y be the number of hours to accomplish the job; so,
8(1/15) = 1/y
which yields y = 15/8
i.e. the job can be completed by 8 typists, working together, in under 2 hours.
Shut the hell up and stop asking the same questions rewording the question.
2006-06-05 16:22:59
·
answer #5
·
answered by Anonymous
·
0⤊
0⤋
16
2006-06-05 16:24:27
·
answer #6
·
answered by Anonymous
·
0⤊
0⤋
6 hrs/3 copiers = 2hrs/copier
8 copiers = 16 hours (If all 8 copiers had no mechanical failures, that is.)
2006-06-05 16:27:24
·
answer #7
·
answered by Anonymous
·
0⤊
0⤋
the correct answer is 3/6 *8=4 hours the time to copy wil decrease
2006-06-05 17:32:27
·
answer #8
·
answered by alooo... 4
·
0⤊
0⤋
1 Hour 15 Minutes
2006-06-05 16:26:16
·
answer #9
·
answered by trebor2 6
·
0⤊
0⤋
if like most copiers, it will take longer, because of all the down time trying to keep more copiers running...
2006-06-05 16:34:08
·
answer #10
·
answered by truthteller 5
·
0⤊
0⤋